The rewritten LEG defect exclusions raise questions about what physically existed on a site, and when. Those facts come first, and many sites already record them.
The London Engineering Group has rewritten its defect exclusions for the first time in twenty years. LEG 1/26, LEG 2/26 and LEG 3/26, dated 6 November 2026, were launched at Lloyd's under the aegis of the International Underwriting Association, succeeding the /96 and /06 wordings for new placements. Policies already written on those wordings stay on them. For the first time, the clauses come with a published commentary.
The background is well reported. Two US decisions, in 2023 and 2024, found LEG 3/06 ambiguous. In England, the Court of Appeal in Sky v Riverstone (2024) read damage in a construction all risks policy as a change to the physical nature of property that impaired its value or usefulness. The Supreme Court refused insurers permission to appeal in April 2025. Underneath all of it sits one question: when does a defect become damage?
These are model clauses. LEG and the IUA are clear that parties are free to adopt, amend or disregard them, and that the commentary is not definitive or binding. What follows is not a reading of cover. It is about the facts the wordings raise.
What the three clauses say
All three apply to the Construction All Risks, Erection All Risks or Builders All Risks section of a policy, and each is, in the commentary's words, "specific to Damage caused by a Defect". They differ mainly in what they take away.
LEG 1/26 excludes Damage caused by a Defect outright. The commentary calls it "an absolute exclusion".
LEG 2/26 deducts the cost of putting the Defect right "as if such Defect had been discovered immediately prior to the Damage". In the commentary's words, the Damage is "hypothetically put on hold" while a scheme to rectify the Defect is costed, and that cost comes off the loss.
LEG 3/26 deducts "the additional cost incurred to improve the material, workmanship, design, plan or specification that was utilised". All three exclude intentional damage caused to get at defective property, but LEG 3/26's exclusion of "Access Damage" does not apply where that damage "is necessary for the repair, replacement, reinstatement or rectification of Damage".
They share the same definitions. Damage is "physical loss, or physical destruction, or adverse physical change of property existent at the time such loss, destruction or change occurs". The commentary explains that existent "refers to actual, tangible property, not property that will only exist at a future stage of the construction project". And two sentences appear in all three: "The existence of a Defect shall not constitute Damage", and "The introduction, integration or addition of property which has a Defect to Insured Property shall not constitute Damage".
Read them as questions about a site
Set the drafting aside and most provisions raise a question about the physical state of the works on a particular date.
Damage needs property "existent at the time". So what had actually been built when the change happened, and what was still only on the programme?
A Defect on its own is not Damage. So was there an adverse physical change, or only a defect that had not yet done anything?
Introducing defective property is not, by itself, Damage. So when was the element installed, and when did anything around it first change?
LEG 2/26 asks what rectification would have cost immediately before the Damage. So what did the works look like that day: what had been built over or around the defective element, and what access was there?
LEG 3/26 measures improvement against what "was utilised". So what material, workmanship and design were actually used, and which version of the design was current when the work was done?
And where access damage is in question, how much was opened up, and where did the Damage actually sit?
Each of these starts with a question of fact. How the clause then applies is a matter of interpretation, and it is worked out from those facts.
Where the answers come from today
Today, most of those facts are reconstructed after the loss. They are assembled from diaries, emails, reports, invoices and whatever photographs someone happened to take, often months later, and from the memories of people who may since have moved to another job.
That is not a criticism of anyone involved. It is what happens when the record of a site is kept for running the site, not for answering questions about it later.
What the site already records
Many projects now run technology that records the physical state of the works, much of it continuously, for their own reasons.
Fixed cameras and time-lapse show what stood on a given date, the sequence of work, and when a visible change first appeared. 360 walk-throughs record the condition of internal areas at each capture, including what was later covered up. Progress tracking shows what had been built by a given date against the programme. Moisture, water and weather sensors record exposure, and when it happened. Drone flights capture large sites at each flight. The project's IFC/BIM models record the design as intended at each version.
Together, those sources hold the facts behind many of the questions above, recorded as they happened rather than after the event.
Reality-Driven Intelligence, the open framework published by Evercam, describes five layers: Reality Capture, Ground Truth, Interpretation, Action and Command. The factual questions sit in the first two. What existed, and when it changed, are matters of capture and ground truth. Whether something is a Defect, what caused the Damage, what a rectification scheme would cost and what counts as improvement sit in Interpretation, and they stay with engineers, adjusters, the parties' advisers and, where needed, the courts. A reliable ground truth is what those judgements are made from.
Why it matters during the build
Most of the facts the clauses ask about are created during construction, between the points at which an engineer's attention reaches the site.
A risk engineering fee buys a finite amount of an expert's attention, spread across the visits and reviews a project needs. Between those points, the site keeps moving, and what reaches the engineer arrives second-hand and after the fact. With a continuous record, the engineer can see what was built over what, when water or weather reached the works, and how materials were stored and protected, while there is still time to act on it. It is more risk engineering from the same fee.
Pikt connects to the technology already running on site, and to the project's IFC/BIM models, and gives risk engineers continuous visibility of the projects they oversee: recorded, not assessed.
And if a loss does happen, the question of what stood on that date already has an answer.
What this does not say
It does not interpret any of the three clauses, or say which one should apply to a project. That is for the parties to negotiate, with their own advice.
It does not say a record settles a claim. A record shows what stood, what changed and when. Whether any of that is a Defect or Damage is for others to decide, and the record serves either answer equally. What it reduces is the guesswork about what was there.
And it only covers what the site's technology captured. An element no source observed is not in it.
Pikt - continuous site visibility for construction insurance risk engineering. Pikt is an independent technology company. It is not an insurer, broker or MGA, and gives no insurance advice.
Sources: LEG 1/26, LEG 2/26 and LEG 3/26 Defect Exclusions, and LEG Commentary, 6 November 2026, available through the IUA clauses database · UK Supreme Court, permission to appeal decisions, April 2025 (UKSC/2025/0026) · Insurance Business UK, "LEG defect clauses rewritten for the first time in 20 years", 10 November 2026